How to write a construction change order when one item replaces another

· 5 min read

A customer wants two pendant lights where the accepted estimate shows two basic fixtures. The crew has time, the boxes are right there and the homeowner says to go ahead. Before the old fixtures come off the order, write down what leaves the job, what takes its place, how much the difference is and whether the finish date changes. Give the person who approved the original job a chance to approve that trade.

Here is a worked change order for that kitchen. The numbers are illustrative selling prices. All amounts in the example use the same before-tax basis. The method works on a piece of paper as long as the customer and the crew can identify the same version.

Find the original line before you price the replacement

Pull out the accepted estimate, including any changes already approved. For this example, estimate E-214 covers a kitchen lighting job for $2,400. There are no previous changes. The price includes $120 for two basic fixtures and labor for installing them. Neither fixture has been purchased. The customer wants you to supply two pendants instead, using the two positions already in the estimate.

That last detail sets the boundary. There is no request for a third pendant, a new switch location or repairs to the ceiling finish. If a second person reads the order a week later, they should be able to point to the same two fixture locations. Give the pendants a model and finish as soon as the customer chooses them. A link to a whole lighting collection leaves too much room for error.

Show the credit alongside the new charges

Price the new fixtures at the selling price you are offering for this job. Work out how much extra labor they add over the time you already priced. In this example the shop allows one extra hour total to assemble both pendants and set their drop heights with the homeowner. The original labor for fitting two lights stays in the original estimate.

Change order CO-01, tied to E-214 Calculation Price change
Remove two unpurchased basic fixtures 2 × $60 credit -$120
Supply two selected pendants 2 × $145 +$290
Additional assembly and height adjustment 1 hour × $95 +$95
Net increase $290 + $95 less $120 +$265

Show the revised job total just below the table. The approved job was $2,400. Add $265 and the revised job will be $2,665 before tax. If you show only the $385 in new charges, the customer has to find the missing $120 credit themselves. If you show only $2,665, they have to subtract the original price to find out what they are being asked to approve.

Write the scope in words someone can use on site

A short entry for the form might read, “Replace the two basic fixtures over the island with two customer-selected pendants in brushed nickel, supplied by the shop. Use the two positions shown on E-214. Assemble the pendants and confirm both heights with the homeowner during fitting. Existing switch location and ceiling finish stay as quoted.”

Put the model numbers beside that entry. If one finish costs more or takes longer to get, a photo alone will make a poor purchasing record. A crew member ordering the parts needs to know which finish the approved allowance actually buys. Keep the supplier’s price and availability with your job notes so you can retrace the calculation if the choice changes again.

Give the schedule its own line

Suppose the basic fixtures were available for the original Friday finish, and the supplier confirms the selected pendants for Monday pickup. The homeowner can meet the crew Tuesday to set the heights. Write “Completion moves from Friday, April 9 to Tuesday, April 13, assuming the selected pendants are ready for pickup Monday.” Ask who will confirm the pickup before putting the return visit on the crew sheet.

Tie the payment line to the arrangement for this job. Here the homeowner has already paid $600, and the original terms put the remaining balance at completion. The change leaves that payment timing in place. On approval the revised job price is $2,665, the payment received stays $600, and the remaining balance will be $2,065. The amount of the change and the balance left to pay belong on different lines.

Collect the decision and keep the crew on the same version

Give the change order its own number, date and reference to the accepted estimate. Leave space for the authorized customer and the shop to record approval and date it. Send the same version to the customer, the person ordering materials and the person preparing the final bill. Until the decision comes back, mark the change pending. Do not let a pending price become part of the crew’s purchase list by accident.

If the homeowner approves the pendants but asks about adding a dimmer, answer the dimmer question separately. Crossing out a line on your copy after the customer has signed leaves two different descriptions of the same order. If you need to revise before approval, mark the earlier copy superseded. If the change is already approved, give the next change its own reference and price.

Carry the difference to the final bill once

At closeout, put E-214, CO-01 and the payment record side by side. One clear bill shows the $2,400 original job, the $265 approved change and the $600 payment, leaving $2,065. If your bill already lists the revised $2,665 as its starting total, adding CO-01 again would overcharge the customer $265. The check takes one subtraction and saves the homeowner from having to reconstruct your paperwork.

For a blank starting point, use the free change order template. If you handle change orders in WorkSnap Pro (a paid-plan feature, see pricing), the change order help article covers the steps in the app. Keep the customer’s decision, the changed price and the date together whichever format you use.

Write estimates and invoices from your phone

Build them from saved items, get them signed, and send them before you leave the job.

Start free

The Free plan is free forever. Paid plans come with a 14-day free trial, no credit card required. See pricing