Free Change Order Template

A change order records one thing: how the job and the price changed after the customer signed the original estimate. This template ties the change to the original estimate, shows credits for removed work next to the added work, and puts the net change and the new contract total above the signature line.

Download the template

Free, no email or sign-up. The Word and Excel files open in Google Docs and Google Sheets too.

Example: bathroom remodel: swap the vanity light for three recessed lights on a dimmer

This is the template filled in for a real kind of construction job.

Change order CO-03

August 4, 2026 · Changes estimate EST-1187

Example
Line itemQtyRateAmount

Credit: vanity light fixture install removed from scope

Was on the original estimate; fixture not yet purchased

1-$82.02-$82.02

Recessed downlight installed in an existing ceiling, per light (labor)

Three lights over the vanity and shower

3$102.52$307.56

Dimmer switch installed (dimmer included)

Replaces the standard switch at the door

1$96.29$96.29

Change order administration

Revised drawings and schedule update

1$32.18$32.18
Net change, this change order+$354.01
Original contract total (EST-1187)$8,450.00
Revised contract total$8,804.01

Notes: Downlights are customer-selected. Work on this change starts only after it is signed. The schedule moves by one day.

Terms: The net change is added to the final payment on the original contract. All other terms of the original estimate stay the same.

Prices are examples only, before any sales tax, from a researched starter price book. The original contract total is illustrative. Use your own costs and rates.

What to put on a construction change order

The original estimate number

Every change order should name the estimate or contract it changes. Without it, a stack of signed changes cannot be added up at the end of the job.

Credits for work you are no longer doing

When one item replaces another, show the removed item as a credit line and the new item as its own line. The customer sees both sides of the swap instead of one unexplained number.

Net change and new total

Show the net change, the original contract total and the revised total. The revised total is the number both of you will check at the final invoice.

Schedule impact and signature

Say whether the change moves the finish date, and get a signature and date before the work starts. A change you do first and price later is the hardest one to collect.

Common mistakes

  • Starting the extra work on a verbal yes and writing the change order afterward.
  • Adding the new item without crediting the one it replaced.
  • No reference to the original estimate, so changes cannot be reconciled at the end.
  • Forgetting to say when the change gets paid: now, at the next milestone, or at the final payment.

Questions

Is this change order template free?

Yes. Download the PDF, Word or Excel version with no email or sign-up. Use it for as many jobs as you like.

Are the prices in the example real?

The line items are examples from WorkSnap Pro's starter price books, which are a researched starting point, not a market quote. The original contract total is illustrative. Use your own numbers.

When do I need a change order?

Any time the scope, price or schedule changes after the customer approved the original estimate: an upgraded fixture, an added room, or a problem found behind a wall. Get it signed before you do the changed work.

Can I do change orders on my phone?

Yes. In WorkSnap Pro you create a change order from the original estimate and the customer approves it with a signature from a link. Change orders are on paid plans. The Free plan is free forever. Paid plans come with a 14-day free trial, no credit card required.

Fill this in on your phone instead

Build the same change order in WorkSnap Pro from saved items and send it before you leave the job. Change orders in WorkSnap Pro are on paid plans.