How to price labor and materials so the job still makes money (worked panel upgrade)
· 4 min read
The quickest way to lose money on a job is to guess one total and hope the materials come in under it. Price labor and materials separately, build your labor rate from what your business actually costs to run, and check your margin before the estimate goes out.
All numbers below are examples to show the method. Use your own costs.
Step 1: Build a labor rate from your costs
Your hourly rate has to pay for more than the time on the job. It pays for the truck, insurance, phone, software, the drive between jobs and the hours you spend quoting. Work it out once a year:
- Direct labor cost per hour. What a tech costs you for an hour on the job, including payroll taxes and benefits. Example: $40.00.
- Overhead per billable hour. Add up a year of overhead and divide by the hours you can actually bill. Example: $60,000 overhead over 1,200 billable hours is $50.00 per hour.
- Profit. Decide what share of the rate should be profit. Example: 20 percent.
Then divide your hourly cost by what is left after profit:
($40.00 + $50.00) ÷ (1 − 0.20) = $90.00 ÷ 0.80 = $112.50 per hour
Check it: 20 percent of $112.50 is $22.50, and $112.50 − $22.50 = $90.00, which is exactly your cost. If your rate is below the cost line ($90.00 here), every billable hour loses money no matter how busy you are.
Notice the billable hours. A one-truck shop rarely bills 2,000 hours a year once you take out drive time, estimates, callbacks and the office. Use a number you have actually hit.
Step 2: Mark up materials, and know your margin
Markup and margin are not the same number, and mixing them up is how a "35 percent" job turns into a 26 percent one.
- Markup is added on top of cost. $1,180.00 of material at a 35 percent markup sells for $1,180.00 × 1.35 = $1,593.00.
- Margin is the share of the selling price you keep. On that sale you keep $1,593.00 − $1,180.00 = $413.00, and $413.00 ÷ $1,593.00 = 25.9 percent.
If you actually want a 35 percent margin on materials, divide by what is left instead: $1,180.00 ÷ 0.65 = $1,815.38. Check it: $1,815.38 − $1,180.00 = $635.38, which is 35.0 percent of $1,815.38.
Pick one and use it consistently. Most contractors find a markup easier to apply line by line, as long as they know what margin it produces.
Step 3: Price the job
Here is a 200-amp panel upgrade priced with the numbers above.
| Line | How it's figured | Amount |
|---|---|---|
| Panel, breakers, wire and fittings | $1,180.00 cost × 1.35 markup | $1,593.00 |
| Labor | 8 hours × $112.50 | $900.00 |
| Permit | Pass-through at cost | $150.00 |
| Subtotal before tax | $2,643.00 |
Sales tax depends on your state and on whether labor is taxable there, so add it the way your state requires.
Keep the permit as its own line at cost. Customers understand a permit fee, and marking it up invites a hard question.
Step 4: Adjust for the conditions you will actually find
The same panel swap takes longer in a finished basement than on an open garage wall. Rather than raising the price with no explanation, add time for the conditions:
- Tight crawlspaces or attics
- Occupied homes where you protect floors and furniture
- Cutting into and patching finished walls
- Finishing a job another contractor started
If this panel sits behind a finished wall that needs an extra 2 hours, add 2 × $112.50 = $225.00 as its own labor line and say why. The customer can see what the extra money buys.
Step 5: Check it before you send it
- Did you include every material you will actually buy, including fittings and consumables?
- Are the hours realistic for these conditions, not a best case?
- Is the total in line with similar jobs you have won and made money on?
- Does the estimate say what is not included?
When the honest price is too high
Sometimes the right price is more than the customer wants to spend. You have three clean options: reduce the scope, offer a good-better-best set of options (see good-better-best pricing), or walk away. Cutting your labor rate below cost to win the job just moves the loss to the end of the month.
Close the loop after the job
When the job is done, compare the hours and material cost you estimated with what you actually spent. If similar jobs keep running 2 hours over, raise the allowance on the next one. This is the only way your prices get more accurate, and it only works if labor and materials were separate on the estimate.
Saving the work for next time
Once you have priced a task a few times, save it. In WorkSnap Pro, items in your price book drop onto an estimate with their description and price, and you can still edit the quantity or rate for each job. Starter catalogs give you a starting list of common trade items, but their prices are rough examples, not quotes: replace them with your own costs before you rely on them.
Start from a free electrical estimate template or plumbing estimate template, or read time and materials vs. flat rate to decide how to present the price. The Free plan is free forever. Paid plans come with a 14-day free trial, no credit card required.